Rising KashmirRising KashmirRising Kashmir
  • Home
  • Top Stories
  • News
    • Kashmir
    • City
    • Jammu
    • Politics
  • Health
  • Anchor
  • Features
  • Interview
  • Video
Search

Archives

  • May 2025
  • April 2025
  • March 2025
  • February 2025
  • January 2025
  • December 2024
  • November 2024
  • October 2024
  • September 2024
  • August 2024
  • July 2024
  • June 2024
  • May 2024
  • April 2024
  • March 2024
  • February 2024
  • January 2024
  • December 2023
  • November 2023
  • October 2023
  • September 2023
  • August 2023
  • July 2023
  • June 2023
  • May 2023
  • April 2023
  • March 2023
  • February 2023
  • January 2023
  • December 2022
  • November 2022
  • October 2022
  • September 2022
  • August 2022
  • July 2022
  • June 2022
  • May 2022

Categories

  • Anchor
  • Breaking
  • Business
  • City
  • Developing Story
  • Editorial
  • Education
  • Features
  • Health
  • Interview
  • Jammu
  • Jammu and Kashmir News
  • Kashmir
  • Kashmir Tourism
  • Kath Bath
  • National
  • Opinion
  • Politics
  • Sports
  • Technology
  • Top Stories
  • Trending
  • Uncategorized
  • Video
  • Viewpoint
  • World
© 2022 Foxiz News Network. Ruby Design Company. All Rights Reserved.
Reading: CS reviews progress on ongoing road projects; says survey underway to cover unconnected habitations under PMGSY IV
Share
Notification Show More
Font ResizerAa
Rising KashmirRising Kashmir
Font ResizerAa
  • Home
  • Top Stories
  • News
  • Health
  • Anchor
  • Features
  • Interview
  • Video
Search
  • Home
  • Top Stories
  • News
    • Kashmir
    • City
    • Jammu
    • Politics
  • Health
  • Anchor
  • Features
  • Interview
  • Video
Follow US
© 2024. All Rights Reserved.
Rising Kashmir > Blog > Breaking > CS reviews progress on ongoing road projects; says survey underway to cover unconnected habitations under PMGSY IV
Breaking

CS reviews progress on ongoing road projects; says survey underway to cover unconnected habitations under PMGSY IV

RK Online Desk
Last updated: January 27, 2025 4:58 pm
RK Online Desk
Published: January 27, 2025
Share
5 Min Read
SHARE

Jammu, Jan  27: Chief Secretary, Atal Dulloo, today chaired a meeting of Public Works Department (PWD) attended by the Engineers of the executing agencies to review progress on major ongoing road projects in Jammu and Kashmir.

While taking stock of overall progress on accomplishing these vital road connectivity links across the UT, the Chief Secretary emphasised on enhancing the capacity of the engineers to enable them in meeting deadlines efficiently.

He directed the senior functionaries to monitor the works themselves for timely completion. He maintained that these road projects are highly significant and need to be completed expeditiously while observing all quality parameters and supervision by the senior officers from the concerned agencies.

He emphasised early completion of survey and formulation of DPRs under PMGSY IV so that all of the unconnected habitations are provided all weather road links under this programme without any fail. He advised the Secretary to regularly monitor this process and complete the requisite Comprehensive New Connectivity Priority List (CNCPL) in respect of each village so that due priority is given to them for early execution and completion.

In a presentation, Secretary PWD, Bhupinder Kumar, apprised the meeting of the achievements made under PMGSY I, II and III. He informed that under PMGSY-I a road length of 17578 Km was constructed including 210 Long Span Bridges (LSBs) and 7 LSBs stands completed under phase II while 1248 km road including a LSB was constructed under phase III of this programme.

The meeting discussed the action plan for completion of remaining works of earlier phases of PMGSY. It also took note of the rolling out of PMGSY IV and its scope of implementation in the UT. The list of unconnected habitations and their survey over the ‘Gram Sadak Survey app’ and the status of preparation of CNCPL for each proposed habitation at block/district level was debated threadbare in the meeting.

It was revealed that J&K being in special category along with NE states would be given assistance to the extent of 90% by the central government under PMGSY. It also has a relaxation in terms of population criteria as the habitations here need to have a population of 250 only instead of 500 for other States/UTs with legislatures.

The meeting was apprised that out of the 1386 unconnected villages in J&K, Gram Sadak Survey in favour of 1249 villages had been finalised and those of 102 is under scrutiny to take them up under PMGSY phase IV for execution.

About Central Road Infrastructure Fund (CRIF), it was divulged that out of 121 ongoing projects sanctioned at a cost of Rs2366 crore an expenditure of Rs 1180 crore had been incurred till date and 21 projects stands completed against the target of 41 projects for the year 2024-25.

With respect to NABARD RIDF, it was given out that 1098 projects were sanctioned under RIDFs XXIV to XXIX to be completed at a cost of Rs4761 crore. Out of these, an expenditure of Rs 1246 crore had been recorded and 195 projects completed till date. It was added that under RDIF-XXX the UT has submitted 140 projects for approval costing around Rs949 crore.

Regarding the overall performance registered under Capex for the financial year 2024-25, the meeting was informed that 2115 works stands completed as on date against the target of 3469 works sanctioned under Road Sector, NABARD, Cities & Towns, CRIF, PMGSY, Bridges programme and other heads of development.

As far as blacktopping of roads is concerned, it was divulged that a total of 3013 km of roads had been macadamised during the ensuing financial year under different sectors of development. Moreover, 25 bridges had also been completed against the target of 60 fixed for this fiscal.

The Chief Secretary also took appraisal of the progress achieved on major road projects executed in different parts of J&K under various schemes. He asked about the current status of their completion with the possible dates of completion. He also directed for completion of all projects on due date so that there is no more slippage in timelines fixed for them.

Other issues that came up for discussion in the meeting included merger of JKPCC staff in PWD and utilisation of funds still lying with the Corporation for finishing of incomplete projects left out by it.

Parliament scuffle case against Rahul Gandhi transferred to Crime Branch: Delhi Police
134 flights delayed, 22 trains running late as dense fog grips Delhi
Jamia Millia Islamia announces sharp fee hike across courses for 2025-26
Traffic resumes from Chenani-Nashri tunnel: SP Ramban
Drug peddler held along with contraband substance in Baramulla
TAGGED:Atal DullooRoad projects

Sign Up For Daily Newsletter

Be keep up! Get the latest breaking news delivered straight to your inbox.
By signing up, you agree to our Terms of Use and acknowledge the data practices in our Privacy Policy. You may unsubscribe at any time.
Share This Article
Facebook Whatsapp Whatsapp Copy Link Print
Previous Article Handicrafts & Handloom Dept hails Master Craftsmen conferred Padma Shri, JK Govt Awards 2025
Next Article Jasprit Bumrah named ICC Men’s Test Cricketer of the Year for 2024
Leave a Comment Leave a Comment

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Stay Connected

1MFollowersLike
262kFollowersFollow
InstagramFollow
234kSubscribersSubscribe
Google NewsFollow

Latest News

Traffic police crackdown on underage drivers near Dal Lake
City
May 18, 2025
Admin rolls out overhaul of Civil Defence Network in Poonch
Jammu
May 18, 2025
CTTIK petitions CM Omar for relief package, tourism revival plan
Jammu
May 18, 2025
GDC Ganderbal hosts essay writing competition on ‘Fostering Moral Values’
Kashmir
May 18, 2025

Recent Posts

  • Traffic police crackdown on underage drivers near Dal Lake
  • Admin rolls out overhaul of Civil Defence Network in Poonch
  • CTTIK petitions CM Omar for relief package, tourism revival plan
  • GDC Ganderbal hosts essay writing competition on ‘Fostering Moral Values’
  • Shrine Board’s Skill, Simulation Lab launches trainings at SMVDIME

Recent Comments

  1. SavePlus on AI and Behavioural Analytics in Gaming: Making the World of Gaming Better
  2. Parul on Govt acknowledges faulty streetlights on Narbal-Tangmarg road
  3. dr gora on Women Veterinarians and the Goal of Viksit Bharat
  4. jalwa game login on National Education Policy 2020: Transforming India’s Educational System
  5. Virender Bhat on Pahalgam Attack: A War on Humanity, Peace, and Kashmiriyat

Contact Us

Flat No 7,Press Enclave, Srinagar, 190001
0194 2477887
9971795706
[email protected]
[email protected]

Quick Link

  • E-Paper
  • About Us
  • Contact Us

Top Categories

Stay Connected

1.06MLike
262.5kFollow
InstagramFollow
234.3kSubscribe
WhatsAppFollow
Rising KashmirRising Kashmir
Follow US
© 2025. All Rights Reserved.
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?