Rising KashmirRising KashmirRising Kashmir
  • Home
  • Top Stories
  • News
    • Kashmir
    • City
    • Jammu
    • Politics
  • Health
  • Anchor
  • Features
  • Interview
  • Video
Search

Archives

  • June 2025
  • May 2025
  • April 2025
  • March 2025
  • February 2025
  • January 2025
  • December 2024
  • November 2024
  • October 2024
  • September 2024
  • August 2024
  • July 2024
  • June 2024
  • May 2024
  • April 2024
  • March 2024
  • February 2024
  • January 2024
  • December 2023
  • November 2023
  • October 2023
  • September 2023
  • August 2023
  • July 2023
  • June 2023
  • May 2023
  • April 2023
  • March 2023
  • February 2023
  • January 2023
  • December 2022
  • November 2022
  • October 2022
  • September 2022
  • August 2022
  • July 2022
  • June 2022
  • May 2022

Categories

  • Anchor
  • Breaking
  • Business
  • City
  • Developing Story
  • Editorial
  • Education
  • Features
  • Health
  • Interview
  • Jammu
  • Jammu and Kashmir News
  • Kashmir
  • Kashmir Tourism
  • Kath Bath
  • National
  • Opinion
  • Politics
  • Sports
  • Technology
  • Top Stories
  • Trending
  • Uncategorized
  • Video
  • Viewpoint
  • World
© 2022 Foxiz News Network. Ruby Design Company. All Rights Reserved.
Reading: AIIMS Awantipora expected to be functional by Nov 2025
Share
Notification Show More
Font ResizerAa
Rising KashmirRising Kashmir
Font ResizerAa
  • Home
  • Top Stories
  • News
  • Health
  • Anchor
  • Features
  • Interview
  • Video
Search
  • Home
  • Top Stories
  • News
    • Kashmir
    • City
    • Jammu
    • Politics
  • Health
  • Anchor
  • Features
  • Interview
  • Video
Follow US
© 2024. All Rights Reserved.
Rising Kashmir > Blog > Kashmir > AIIMS Awantipora expected to be functional by Nov 2025
Kashmir

AIIMS Awantipora expected to be functional by Nov 2025

CS asks to increase manpower, step up efforts for speedy completion

RK News
Last updated: January 18, 2025 1:34 am
RK News
Published: January 18, 2025
Share
3 Min Read
SHARE

Jammu, Jan 17: Chief Secretary, Atal Dulloo, today held a joint meeting of the authorities of All India Institute of Medical Sciences (AIIMS), Awantipora, Health & Medical Education, PWD, Jal Shakti and CPWD regarding early completion of this vital health facility in the region.
Those who attended the meeting included Executive Director, AIIMS, Awantipora, Divisional Commissioner, Kashmir, Secretary, PWD, Secretary, H&ME, Deputy Commissioner, Pulwama, Chief Engineer, CPWD, DG, Budget besides others.
The Chief Secretary assessed the status of physical infrastructure raised at the site, so far, along with proposed dates of its completion. He enquired about the current status of labourers available for execution of work there and impressed upon the agency to enhance their number immediately after the winter season is over.
He also reviewed the water supply scheme and the approach road leading to the institute. He directed the Jal Shakti Department to complete the first phase of the WSS including 3 bore wells and other allied works by May this year for providing adequate water supply to the hospital to become functional.
Dulloo further assessed the additional land and other requirements for future expansion of this project. He enquired from the Executive Director about any of the pending issues deserving administrative support and simultaneously assured him of all possible assistance.
Executive Director (ED), AIIMS Awantipora, Dr Sachidananda Mohanty, provided overall scenario of the readiness of this facility along with the possible dates of completion of each block. He revealed that the institute has achieved overall physical progress of about 61% on all the 57 blocks to be raised here. He gave out that the institute is expected to be made functional by the end of November this year.
The meeting was further apprised of the detailed labour force deployed in completion of each block. It was said that due to cold weather conditions the labourers had migrated and only internal works are currently going on with the presence of around 850 skilled/semi-skilled/unskilled labourers which earlier used to be around 2400-2500 under fair weather conditions.
It was further disclosed that the work is going on all the 6 hospital blocks, 4 academic blocks, 16 residential blocks, 12 hostel blocks along with Ayush block besides night shelter and guest house, which are part of this medical college and hospital of national repute.

 

Centre agrees to discuss 4-point agenda with Ladakhi leaders
Orchard sanitation critical to prevent plant diseases: SKAUST  
ADDC Budgam chairs meeting on Ayushman Bhava campaign
Shalini Yadav inaugurates ‘skill dev centre’ in Srinagar
PCCF inspects demarcation, dev works in south Kashmir

Sign Up For Daily Newsletter

Be keep up! Get the latest breaking news delivered straight to your inbox.
By signing up, you agree to our Terms of Use and acknowledge the data practices in our Privacy Policy. You may unsubscribe at any time.
Share This Article
Facebook Whatsapp Whatsapp Copy Link Print
Previous Article IUST secures 4-Star ranking for promoting innovation, entrepreneurship
Next Article Traffic violations: Rs 28.36 cr revenue generated in 2024
Leave a Comment Leave a Comment

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Stay Connected

1MFollowersLike
262kFollowersFollow
InstagramFollow
234kSubscribersSubscribe
Google NewsFollow

Latest News

J&K Govt revolutionises digital governance with High Impact Cyber security Workshop
Breaking
June 18, 2025
CM Omar Abdullah chairs high-level meeting to finalize Muharram arrangements
Developing Story Jammu and Kashmir News
June 18, 2025
Statehood is our right, not a favour: Farooq Abdullah
Breaking
June 18, 2025
Iran leader rejects Trump’s call for surrender; Trump says patience has run out
Breaking World
June 18, 2025

Recent Posts

  • J&K Govt revolutionises digital governance with High Impact Cyber security Workshop
  • CM Omar Abdullah chairs high-level meeting to finalize Muharram arrangements
  • Statehood is our right, not a favour: Farooq Abdullah
  • Iran leader rejects Trump’s call for surrender; Trump says patience has run out
  • “Zionist regime made grave mistake; will face consequences of its actions”: Iran’s supreme leader

Recent Comments

  1. Shah on Relief for Employees: J&K Bank Fixes EMI-Credit Mismatch, says JK Bank Chairman
  2. Latif khan on Why Kashmir needs Stronger Private Healthcare and Health Insurance
  3. Sameer farooq mir on Qazi Irfan assumes charge as RTO Kashmir
  4. Captain Vikrama on CM Omar Abdullah hails historic feat as three Kashmiri Girls crack IIT-JEE Advanced
  5. BASHIR AHMAD BHAT on Poor hotel accommodation, lack of medical facilities irk Kashmiri pilgrims in Saudi Arabia, video goes viral

Contact Us

Flat No 7,Press Enclave, Srinagar, 190001
0194 2477887
9971795706
[email protected]
[email protected]

Quick Link

  • E-Paper
  • About Us
  • Contact Us

Top Categories

Stay Connected

1.06MLike
262.5kFollow
InstagramFollow
234.3kSubscribe
WhatsAppFollow
Rising KashmirRising Kashmir
Follow US
© 2025. All Rights Reserved.
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?