Rising KashmirRising KashmirRising Kashmir
  • Home
  • Top Stories
  • News
    • Kashmir
    • City
    • Jammu
    • Politics
  • Health
  • Anchor
  • Features
  • Interview
  • Video
Search

Archives

  • May 2025
  • April 2025
  • March 2025
  • February 2025
  • January 2025
  • December 2024
  • November 2024
  • October 2024
  • September 2024
  • August 2024
  • July 2024
  • June 2024
  • May 2024
  • April 2024
  • March 2024
  • February 2024
  • January 2024
  • December 2023
  • November 2023
  • October 2023
  • September 2023
  • August 2023
  • July 2023
  • June 2023
  • May 2023
  • April 2023
  • March 2023
  • February 2023
  • January 2023
  • December 2022
  • November 2022
  • October 2022
  • September 2022
  • August 2022
  • July 2022
  • June 2022
  • May 2022

Categories

  • Anchor
  • Breaking
  • Business
  • City
  • Developing Story
  • Editorial
  • Education
  • Features
  • Health
  • Interview
  • Jammu
  • Jammu and Kashmir News
  • Kashmir
  • Kashmir Tourism
  • Kath Bath
  • National
  • Opinion
  • Politics
  • Sports
  • Technology
  • Top Stories
  • Trending
  • Uncategorized
  • Video
  • Viewpoint
  • World
© 2022 Foxiz News Network. Ruby Design Company. All Rights Reserved.
Reading: J-K chief secretary fixes timeline for completion of various developmental works
Share
Notification Show More
Font ResizerAa
Rising KashmirRising Kashmir
Font ResizerAa
  • Home
  • Top Stories
  • News
  • Health
  • Anchor
  • Features
  • Interview
  • Video
Search
  • Home
  • Top Stories
  • News
    • Kashmir
    • City
    • Jammu
    • Politics
  • Health
  • Anchor
  • Features
  • Interview
  • Video
Follow US
© 2024. All Rights Reserved.
Rising Kashmir > Blog > Breaking > J-K chief secretary fixes timeline for completion of various developmental works
Breaking

J-K chief secretary fixes timeline for completion of various developmental works

ANI
Last updated: February 28, 2023 10:37 am
ANI
Published: February 28, 2023
Share
3 Min Read
SHARE

Jammu and Kashmir chief secretary, Arun Kumar Mehta on Monday took an on-spot assessment of different developmental works taken up under Smart City and by other executing agencies around the city and also fixed timeline for completion of each.

On the occasion, the chief secretary was accompanied by the Divisional Commissioner, Kashmir; Deputy Commissioner, Srinagar; Commissioner, SMC; VC, LCMA; and many other concerned officers of Police and Civil administration. Mehta observed that the city is going to change for better by mid-April this year.

He said that the city is going to change its outlook altogether with the completion of these projects at different stages of execution presently.

“These works would give a massive facelift to the city thereby enhancing its appeal for all the residents and tourists,” he said.

According to an official statement, the chief secretary visited different project sites under Smart City Mission. He took stock of the progress of work on each of them and passed on several directions for their early completion.

He stressed on timely completion of all these works in the wake of the upcoming tourist season.

While taking an on-spot assessment of the Jhelum Riverfront development the chief secretary enjoined the officers to complete the work by April 15.

“He asked them to develop the footpath including its finishing, cycle track, green spaces, landscaping and undergrounding of electrical cables etc forthwith. The project is to be completed at a cost of Rs 32.50 crore,” the statement said.

“At Polo View, the chief secretary emphasized on making the entire area aesthetically appealing adopting an integrated approach. He asked for facade improvement of adjoining buildings and carry out other beautification works simultaneously,” it added.

On a visit to Dal Lake, Mehta inspected the work of lakefront development along the Northern Foreshore Road of the Lake from Nishat to Naseem Bagh including a pedestrian walkway. The development also has components of cycle track construction & viewing decks.

He urged the authorities to ensure its completion by of April 15 this year. He also instructed for completing the lighting of Western Fore Shore Road by March 15.

The chief secretary highlighted the need for connecting all the houseboats with the STPs. He directed for utilizing of the 36 MLD capacity of Sewage Treatment optimally and connect all the 900 houseboats in the lake with the Sewage lines.
He asked them to divert the residual to oxidation ponds out of the 48 MLD produced daily.

He exhorted upon the concerned to start the motorboats to commence their cruise and initiate water sports activities in the lake by March 15. (ANI)

Pampore Constituency : PDP’s Zahoor Mir leads by 9 votes for the 4th round of counting
Twitter suffers major outage, several users face trouble signing in
Cyclone Hamoon to cross Bangladesh coast by early hours of tomorrow: IMD
Situation normal at Jammu, Poonch; no shelling reported overnight
Trump reinstates “maximum pressure” on Iran, withdraws US from UNHRC

Sign Up For Daily Newsletter

Be keep up! Get the latest breaking news delivered straight to your inbox.
By signing up, you agree to our Terms of Use and acknowledge the data practices in our Privacy Policy. You may unsubscribe at any time.
Share This Article
Facebook Whatsapp Whatsapp Copy Link Print
Previous Article Nirmala Sitharman visits Sikkim for Budget Outreach programme
Next Article Awantipora Gunfight: Militant Killed Identified: ADGP Kashmir
Leave a Comment Leave a Comment

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Stay Connected

1MFollowersLike
262kFollowersFollow
InstagramFollow
234kSubscribersSubscribe
Google NewsFollow

Latest News

Hyderpora underpass turns into cab stand, sparks safety concerns
City
May 26, 2025
Bear-Proof Corral unveiled to tackle human-wildlife conflict in Drass
Kashmir
May 26, 2025
SACPPE holds session to safeguard children from unexploded shells in Uri
Kashmir
May 26, 2025
‘Prem Visheshagya’ brings laughter to Natrangs’ Sunday theatre
Jammu
May 26, 2025

Recent Posts

  • Hyderpora underpass turns into cab stand, sparks safety concerns
  • Bear-Proof Corral unveiled to tackle human-wildlife conflict in Drass
  • SACPPE holds session to safeguard children from unexploded shells in Uri
  • ‘Prem Visheshagya’ brings laughter to Natrangs’ Sunday theatre
  • Admin spreads awareness on drug abuse in Sgr

Recent Comments

  1. SavePlus on AI and Behavioural Analytics in Gaming: Making the World of Gaming Better
  2. Parul on Govt acknowledges faulty streetlights on Narbal-Tangmarg road
  3. dr gora on Women Veterinarians and the Goal of Viksit Bharat
  4. jalwa game login on National Education Policy 2020: Transforming India’s Educational System
  5. Virender Bhat on Pahalgam Attack: A War on Humanity, Peace, and Kashmiriyat

Contact Us

Flat No 7,Press Enclave, Srinagar, 190001
0194 2477887
9971795706
[email protected]
[email protected]

Quick Link

  • E-Paper
  • About Us
  • Contact Us

Top Categories

Stay Connected

1.06MLike
262.5kFollow
InstagramFollow
234.3kSubscribe
WhatsAppFollow
Rising KashmirRising Kashmir
Follow US
© 2025. All Rights Reserved.
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?