Chief Executive Officer, Jammu and Kashmir Economic Reconstruction Agency (ERA), Dr. Syed Sehrish Asgar today impressed upon all officers of J&K ERA to ensure timely handover of all sub projects completed under the World Bank funded Jhelum Tawi Flood Recovery Project to user departments.
She said this while chairing the periodic meeting held to review progress on ongoing World Bank funded Jhelum Tawi Flood Recovery Project at Civil Secretariat, Srinagar here today.
While reviewing progress on under execution sub projects being executed under JTFRP, Dr. Syed Sehrish Asgar was informed that the work on upgradation of 47 dewatering stations in Srinagar city is at advanced stage with work already completed on 40 stations while as work on remaining 7 stations will be completed by March, 2024.