Jammu and Kashmir Chief Minister Omar Abdullah on Saturday provided an update on the restoration of power in Kashmir following the heavy snowfall.
In a post on X, CM wrote, “Out of forty one 33KV feeders dysfunctional in Kashmir due to heavy snowfall, thirty seven have been restored and charged.”
“Similarly, out of 739 dysfunctional 11KV feeders,
639 have been restored and recharged, bringing a major relief to the valley. The majority of the rest are expected to be restored by the evening.” he added.
He also praised the Power Development Department (PDD) for their relentless efforts, “Kudos to the PDD team for their relentless efforts in this snow fall in such a short time.” CM said.