Rising KashmirRising KashmirRising Kashmir
  • Home
  • Top Stories
  • News
    • Kashmir
    • City
    • Jammu
    • Politics
  • Health
  • Anchor
  • Features
  • Interview
  • Video
Search

Archives

  • May 2025
  • April 2025
  • March 2025
  • February 2025
  • January 2025
  • December 2024
  • November 2024
  • October 2024
  • September 2024
  • August 2024
  • July 2024
  • June 2024
  • May 2024
  • April 2024
  • March 2024
  • February 2024
  • January 2024
  • December 2023
  • November 2023
  • October 2023
  • September 2023
  • August 2023
  • July 2023
  • June 2023
  • May 2023
  • April 2023
  • March 2023
  • February 2023
  • January 2023
  • December 2022
  • November 2022
  • October 2022
  • September 2022
  • August 2022
  • July 2022
  • June 2022
  • May 2022

Categories

  • Anchor
  • Breaking
  • Business
  • City
  • Developing Story
  • Editorial
  • Education
  • Features
  • Health
  • Interview
  • Jammu
  • Jammu and Kashmir News
  • Kashmir
  • Kashmir Tourism
  • Kath Bath
  • National
  • Opinion
  • Politics
  • Sports
  • Technology
  • Top Stories
  • Trending
  • Uncategorized
  • Video
  • Viewpoint
  • World
© 2022 Foxiz News Network. Ruby Design Company. All Rights Reserved.
Reading: DC Srinagar reviews progress of developmental works under R&B Sector
Share
Notification Show More
Font ResizerAa
Rising KashmirRising Kashmir
Font ResizerAa
  • Home
  • Top Stories
  • News
  • Health
  • Anchor
  • Features
  • Interview
  • Video
Search
  • Home
  • Top Stories
  • News
    • Kashmir
    • City
    • Jammu
    • Politics
  • Health
  • Anchor
  • Features
  • Interview
  • Video
Follow US
© 2024. All Rights Reserved.
Rising Kashmir > Blog > Breaking > DC Srinagar reviews progress of developmental works under R&B Sector
Breaking

DC Srinagar reviews progress of developmental works under R&B Sector

RK Online Desk
Last updated: June 6, 2023 8:37 pm
RK Online Desk
Published: June 6, 2023
Share
7 Min Read
SHARE

In order to review the progress of developmental works taken up under R&B Sector in the District during financial year 2023-24, a meeting of concerned Officers was held under the Chairmanship of Deputy Commissioner(DC) Srinagar, Mohammad Aijaz Asad here on Tuesday at Meeting Hall of the DC Office Complex.

At the outset, the Deputy Commissioner took a comprehensive physical/financial review of targets with regard to infrastructure development, upgradation works and macadamization process undertaken by R&B Circle Srinagar/Budgam, R&B Circular Road Project, PMGSY, NABARD, City Roads Division etc.

On the occasion, the DC was given apprised about present status of major developmental works and macadamization process through detailed PowerPoint presentations by the concerned Superintending Engineers.

Giving details of the Circle, the Superintendent Engineer R&B Circle Srinagar/Budgam informed that as many as 33 works have been approved at a cost of Rs 24.0 crore with a target to macadamize/blacktop the roads. While Rs 4.48 crore are also being spent on filling of potholes on 12.70 kilometers of road in CD-1st, CD-2nd, Chadoora and PCD-Ist Division of Srinagar District.

In addition, 44 works have also been completed to blacktop 117.91 Km road length at a cost of Rs 31.07 Cr during G20 programmes.

Similarly, the Superintendent Engineer(R&B) Circular Road Project informed the DC that a road length is being black topped during the current FY in the Circle at a cost of Rs 6.48 crore.

With regard to filling of Potholes, the DC stressed on completing the works on priority basis to ensure hassle-free movement of commuters. He also asked the concerned to ensure early completion of works taken up under Srinagar Smart City projects.

The DC was further informed that under NABARD, 8 works have been approved to blacktop roads at the cost of Rs 11.50 crore.

It was also given out that work on construction/ upgradation of Daggapora-Anchar road is going on at a cost of Rs 2.57 crore. While upgradation of road from Chahtterhama to Hadoora via Khimber along S.E Canal including allied links is also being carried out at Rs 2.31 core to benefit the local habitations.

Under District-Sector, 2023-24 as many as 11 works are approved with an outlay of Rs 1.42 crore for developmental works.

While reviewing the progress of works being executed under PMGSY schemes, the DC was informed that 10.95 km road length is being macadamized under PMGSY-3 in Mirpora via Achar-DugaPora and Mujgund to Panzinara via Rambir Garh areas of the District.

The DC also took a detailed review of Status of SAMAGRA Works and Proposed Budget 2023-24 under District Capex Budget for school Education of the District.

The Deputy Commissioner after taking review of all works being executed during the current year under R&B and other allied sectors directed the officers to strictly follow the deadlines of each project to ensure their timely completion so that people are benefitted at large.

The DC laid stress on speeding up the pace of execution process to complete the works in a time bound manner. He exhorted upon the concerned Officers to monitor the progress of works on daily basis by maintaining work wise Pert-Chart.

The DC asked the officers to work with added zeal and due diligence to ensure that DPRs of all development projects must incorporate all aspects of that infrastructure like boundary wall, furniture, landscaping etc so that the asset is completed in one go for its better utilization.

The DC stressed the officers to work with a vision of development and welfare of the people and make sure that all the projects are completed within the stipulated time frame with strict adherence to the quality standards.

During the meeting the DC took first hand appraisal about the progress on ongoing major development projects including 127-meter long Noor-Jehan Bridge on Jhelum river at Qamarwari being constructed at a cost of Rs 10 crore.

The DC also reviews progress of ongoing works on construction of flyovers and Nowgam Junction, Bemina Crossing and Sanat Nagar being carried out at a cost of Rs 34.90 crore, Rs 31.49 crore and Rs 41 crore respectively with the aim to decongest the City areas and ensure smooth ply traffic on National Highway.

The DC was informed that work is going in full swing on Nowgam and Bemina Flyovers and shall be made operational by September this year while Sanat Nagar flyover will be completed by November 2023

While reviewing progress of work on the Rs 7.42 crore project for construction of second Tankipora bridge adjacent to DC Office Complex, the DC stressed the officers to accelerate the pace of work and complete the construction of the vital project.

Similarly, the DC asked the Officers to start work on construction of Footbridge over the Kut-kul to connect the parking facility in Old Secretariat premises with Amar Niwas Complex housing offices of the Financial Commissioner Revenue (FCR), Divisional Commissioner, Kashmir and Deputy Commissioner Srinagar.

Chief Planning Officer, Mohammad Yaseen Lone, Superintendent Engineer R&B Circle Srinagar/Budgam, Sajad Naqeeb, Superintending Engineer R&B CRP, Mohammad Maqbool, Chief Education Officer, Mohammad Shabir District Health Officer, Dr Asifa and Executive Engineer R&B City Roads, Besides, Executive Engineers of R&B, PMGSY, SAMAGRA and other concerned Officers were present in the meeting.

J&K Govt approves Rs 329 cr 5 year project to achieve self reliance in Mutton sector
7 bank cases settled at Samba Lok Adalat
Youth injured in wild bear attack in Sonamarg
In a first, football tournament held amid biting cold in Kashmir
Noted lawyer Ashok Bhan briefs NHRC Chairman ahead of visiting Kashmir

Sign Up For Daily Newsletter

Be keep up! Get the latest breaking news delivered straight to your inbox.
By signing up, you agree to our Terms of Use and acknowledge the data practices in our Privacy Policy. You may unsubscribe at any time.
Share This Article
Facebook Whatsapp Whatsapp Copy Link Print
Previous Article Exercise can help reduce risk of type 2 diabetes: Study
Next Article Srinagar Admin organizes Anti Drug awareness program at Government Degree College Hyderpora
Leave a Comment Leave a Comment

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Stay Connected

1MFollowersLike
262kFollowersFollow
InstagramFollow
234kSubscribersSubscribe
Google NewsFollow

Latest News

Tourism comes to grind halt in Sonamarg after Pahalgam terror attack
Kashmir
May 29, 2025
SKUAST-K to establish advanced reproductive biotechnology centre to enhance animal breeding
Kashmir
May 29, 2025
DC calls for intensified action against drug abuse at NCORD review in Gbl
Kashmir
May 29, 2025
Shikara operators continue to ignore mandatory safety protocols
City
May 29, 2025

Recent Posts

  • Tourism comes to grind halt in Sonamarg after Pahalgam terror attack
  • SKUAST-K to establish advanced reproductive biotechnology centre to enhance animal breeding
  • DC calls for intensified action against drug abuse at NCORD review in Gbl
  • Shikara operators continue to ignore mandatory safety protocols
  • IUST partners with government for building safer J&K

Recent Comments

  1. BASHIR AHMAD BHAT on Poor hotel accommodation, lack of medical facilities irk Kashmiri pilgrims in Saudi Arabia, video goes viral
  2. sree vishnu movies on Pahalgam attack shatters Kashmir’s film tourism revival
  3. SavePlus on AI and Behavioural Analytics in Gaming: Making the World of Gaming Better
  4. Parul on Govt acknowledges faulty streetlights on Narbal-Tangmarg road
  5. dr gora on Women Veterinarians and the Goal of Viksit Bharat

Contact Us

Flat No 7,Press Enclave, Srinagar, 190001
0194 2477887
9971795706
[email protected]
[email protected]

Quick Link

  • E-Paper
  • About Us
  • Contact Us

Top Categories

Stay Connected

1.06MLike
262.5kFollow
InstagramFollow
234.3kSubscribe